PLAN
D'INSPECTION TEST & FABRICATION |
#MITP-1423 |
|
DÉPARTEMENT
DE CONTRÔLE DE QUALITÉ |
Page 1 de
1 |
|
Commande
de travail Silentec: |
Date: |
22 Avril 2002 |
Client: |
Revision
# |
2 |
Projet: HRSG
Boitier, conduits & Strucure |
Preparé par: |
L.A.S.Q. |
Composante: |
Revisé par: |
F.C.A. |
Atelier: |
Approuvé
par: |
M.V.E. |
Article |
Description des travaux |
Type
d'Inspection |
Date &
signature d'inspection |
Atelier |
Silentec |
Client |
Atelier |
Silentec |
Client |
1.0 |
LIBERER DESSINS |
H |
R |
|
|
|
|
2.0 |
INSPECTER DIMENSIONS & LIBERER MATÉRIEL |
|
|
|
|
|
|
2.1 |
Plaques acier carbone |
H |
H |
R |
|
|
|
2.2 |
Poutres acier carbone |
H |
H |
R |
|
|
|
2.3 |
Angles acier carbone |
H |
H |
R |
|
|
|
2.4 |
Profilés acier carbone |
H |
H |
R |
|
|
|
2.5 |
Matériel de soudure |
H |
H |
R |
|
|
|
2.6 |
Liners acier inoxydables |
H |
H |
R |
|
|
|
2.7 |
Tuyaux, bride, barres |
H |
H |
R |
|
|
|
2.8 |
Portes, pentures |
H |
H |
R |
|
|
|
2.9 |
Gaskets |
H |
H |
R |
|
|
|
2.10 |
Dimple studs acier inoxydable |
H |
H |
R |
|
|
|
2.11 |
Boulonnerie acier inoxydables |
H |
H |
R |
|
|
|
2.12 |
Quincaillerie acier galvanisé |
H |
H |
R |
|
|
|
2.13 |
Isolation laine minérale |
H |
H |
R |
|
|
|
2.14 |
Peinture |
H |
H |
R |
|
|
|
3.0 |
SOUDURE |
H |
H |
R |
|
|
|
3.1 |
Révision procédures soudure (WPS) |
H |
H |
R |
|
|
|
3.2 |
Révision procédures PQR |
H |
H |
R |
|
|
|
3.3 |
Qualifications soudeurs |
H |
H |
R |
|
|
|
4.0 |
PROCÉDÉ
DE FABRICATION |
H |
H |
R |
|
|
|
4.1 |
Préparer Matérial |
H |
H |
R |
|
|
|
4.2 |
Assembler pièces |
H |
H |
R |
|
|
|
4.3 |
Inspecter assemblage avant soudure |
H |
H |
R |
|
|
|
4.4 |
Soudure |
H |
H |
R |
|
|
|
4.5 |
Inspection visuelle des soudures & dimensions |
H |
H |
R |
|
|
|
4.6 |
Essais Non Destructifs quand requis |
H |
H |
R |
|
|
|
4.7 |
Perforer trous |
H |
H |
R |
|
|
|
4.8 |
Positionner & souder dimple studs |
H |
H |
R |
|
|
|
4.9 |
Tests de pliage & inspecter position
Studs |
H |
H |
R |
|
|
|
4.10 |
Nettoyer & finir surfaces |
H |
H |
R |
|
|
|
4.11 |
Inspection visuelle générale du panneau ( rouille, huile,
scratch, tacks) |
H |
H |
H Random check |
|
|
|
4.12 |
Nettoyer au jet de sable (face
externe) |
H |
H |
R |
|
|
|
4.13 |
Appliquer peinture |
H |
H |
R |
|
|
|
4.14 |
Mesure épaisseur sèche & adhérencee de pellicule |
H |
H |
R |
|
|
|
4.15 |
Installer fibre minérale, péllicule
plastique & rondelles |
H |
H |
R |
|
|
|
4.16 |
Inspecter position fibre minérale |
H |
H |
R |
|
|
|
4.17 |
Installer feuilles liners |
H |
H |
R |
|
|
|
4.18 |
Inspecter position & chevauchement des
liners |
H |
H |
R |
|
|
|
4.19 |
Installer noix & rondelle et tackweld |
H |
H |
R |
|
|
|
4.20 |
Inspecter & approuver composante |
H |
H |
R |
|
|
|
5.00 |
PREPARER POUR EXPÉDITION |
|
|
|
|
|
|
5.1 |
Marquer composante |
H |
R |
R |
|
|
|
5.2 |
Empaqueter & sceller au plastique |
H |
R |
R |
|
|
|
5.3 |
Documents d'expédition & douanes |
|
H |
R |
|
|
|
5.4 |
Entreposer jusqu'à expédition |
H |
W |
|
|
|
|
5.5 |
Superposer & renforcer les composantes |
H |
W |
|
|
|
|
5.6 |
Monter les composantes sur le camion |
H |
W |
|
|
|
|
5.7 |
Inspection final & libérer pour expédition |
H |
H |
H |
|
|
|
LÉGENDE |
|
|
|
|
|
|
H = |
Point d'arrêt |
|
|
|
|
|
|
W= |
Point témoin |
|
|
|
|
|
|
R= |
Revue de documents |
|
|
|
|
|
|